The Sustainable Village is moving right along. About 8 students are now working on the project. Week 7 brought more framing, trusses, plumbing and electrical.

The northwest home is fully framed and wrapped in an exterior air barrier. Lead plumber Dawson worked with several engineering students on the plumbing and mechanical systems. Four self-contained sewage treatment plants were installed this week, one for each home. Students also backfilled soil over the insulated mat foundations.